June → December 2022
Site Development
January 01 → July 21 2023
Building Dry In
July 24 → October 23 2023
Temporary Power
September 18 → October 26 2023
Conditioned Air and Heat Start Up
February 05 → March 04 2024
Substantial Completion
May 01 → June 02 2023
Furniture/Technology/Equipment Set Up