September 17 2024

Community construction update meeting

November 19 2024

Demolition Phase 1 and 2 Mobilization

February 07 2025

Mass Grading and Sitework (expected)

March 26 2025

Structural construction begins (expected)

August 13 2025

Exterior skin construction begins (expected)

August 27 2025

Interior construction begins (expected)

January 01 2026

Sitework finishing (expected)

June 15 2026

Final inspection and testing (expected)